Carrier XRV Especificações Página 180

  • Descarregar
  • Adicionar aos meus manuais
  • Imprimir
  • Página
    / 190
  • Índice
  • MARCADORES
  • Avaliado. / 5. Com base em avaliações de clientes
Vista de página 179
CL-2
-
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - -
CUT ALONG DOTTED LINE CUT ALONG DOTTED LINE
INSPECT WIRING AND RECORD ELECTRICAL DATA:
RATINGS:
Motor Voltage Motor RLA Chiller LRA Rating
Actual Line Voltages: VFD Oil Pump Controls/Oil Heater
Verify 6-in. clearance surrounding all VFD enclosure louvers: Yes No
Visually inspect down through top of power module for debris: Yes No
VFD Manufacturer ___________________________
VFD Serial Number __________________________
Mfd in _____________________________________
VFD Nameplate I.D. Number ___________________
VFD Nameplate Input Rating ___________________
on ________________________________________
FIELD-INSTALLED VFDs ONLY:
Check continuity T1 to T1, etc. (Motor to VFD, disconnect motor leads T1, T2, T3.) Do not megger VFD;
disconnect leads to motor and megger the leads.
CONTROLS: SAFETY, OPERATING, ETC.
Perform Controls Test (Yes/No)
INITIAL START:
Line Up All Valves in Accordance With Instruction Manual:
Start Water Pumps and Establish Water Flow
Oil Level OK and Oil Temperature OK Check Oil Pump Rotation-Pressure
Check Compressor Motor Rotation (Motor End Sight Glass) and Record: Clockwise
Restart Compressor, Bring Up To Speed. Shut Down. Any Abnormal Coastdown Noise? Ye s * No
*If yes, determine cause.
START MACHINE AND OPERATE. COMPLETE THE FOLLOWING:
A: Trim charge and record under Charge Refrigerant Into Chiller section on page 74.
B: Complete any remaining control calibration and record under Controls section (pages 15-57).
C: Take at least two sets of operational log readings and record.
D: After machine has been successfully run and set up, shut down and mark shutdown oil and refrigerant levels.
E: Give operating instructions to owner’s operating personnel. Hours Given: Hours
F: Call your Carrier factory representative to report chiller start-up.
G: Register LiquiFlo2 VFD start-up at www.automation.rockwell.com/complete1/warp.
H: Return a copy of this checklist to the local Carrier Service office.
SIGNATURES:
CARRIER
TECHNICIAN
DATE
CUSTOMER
REPRESENTATIVE
DATE
MEGGER MOTOR
PHASE TO PHASE PHASE TO GROUND
T1-T2 T1-T3 T2-T3 T1-G T2-G T3-G
10-Second Readings: ____ ____ ____ ____ ____ ____
60-Second Readings: ____ ____ ____ ____ ____ ____
Polarization Ratio: ____ ____ ____ ____ ____ ____
PIC III CAUTION
COMPRESSOR MOTOR AND CONTROL PANEL MUST BE PROPERLY AND INDIVIDUALLY
CONNECTED BACK TO THE EARTH GROUND IN THE VFD (IN ACCORDANCE WITH CERTIFIED
DRAWINGS).
Ye s
WATER/BRINE PUMP CONTROL: Can the Carrier controls independently start the pumps?
Condenser Water Pump Ye s No
Chilled Water Pump Ye s No
RUN MACHINE: Do these safeties shut down machine?
Condenser Water Flow Ye s No
Chilled Water Flow Ye s No
Pump Interlocks Ye s No
Vista de página 179
1 2 ... 175 176 177 178 179 180 181 182 183 184 185 ... 189 190

Comentários a estes Manuais

Sem comentários

United States Stove Company Ofen Benutzerhandbücher

Beginnend mit A

Klicken Sie auf den Alphabet unten, um zur vollständigen Liste der Modelle zu gelangen, die mit diesem Buchstaben beginnen

Modelle Dokumententyp
AIR
Bedienungsanleitung   United States Stove Company AIR User Manual, 24 Seiten