
Leak Test Machine — Due to regulations regarding re-
frigerant emissions and the difficulties associated with sepa-
rating contaminants from refrigerant, Carrier recommends
the following leak test procedures. See Fig. 30 for an outline
of the leak test procedures. Refer to Fig. 24 and 25 during
pumpout procedures. See the Pumpout and Refrigerant Trans-
fer Procedures Section on page 61. Refer to Tables 6A-6D
for temperature/pressure relationships for HCFC-22 and HFC-
134a refrigerants. See Fig. 31-34.
1. If the pressure readings are normal for machine
condition:
a. Evacuate the holding charge from the vessels, if present.
b. Raise the machine pressure, if necessary, by adding
refrigerant until pressure is at equivalent saturated pres-
sure for the surrounding temperature.
Never charge liquid refrigerant into the machine if
the pressure in the machine is less than 68 psig
(469 kPa) [35 psig (241 kPa)]. Charge as a gas only,
with the cooler and condenser pumps running, until
this pressure is reached, using PUMPDOWN and TER-
MINATE PUMPDOWN/LOCKOUT mode on the
PIC. Flashing of liquid refrigerant at low pressures
can cause tube freeze-up and considerable
damage.
c. Leak test machine as outlined in Steps3-7.
2. If the pressure readings are abnormal for machine
condition:
a. Prepare to leak test machines shipped with refrigerant.
If machine is shipped with refrigerant, proceed to
Step 2h.
b. Check for large leaks by connecting a nitrogen bottle
and raising the pressure to 30 psig (207 kPa). Soap
test all joints. If the test pressure holds for 30 minutes,
prepare the test for small leaks (Steps 2g - h).
c. Plainly mark any leaks which are found.
d. Release the pressure in the system.
e. Repair all leaks.
f. Retest only those joints that were repaired.
g. After successfully completing the test for large leaks,
remove as much nitrogen, air, and moisture as pos-
sible, given the fact that small leaks may be present in
the system. This can be accomplished by following
the dehydration procedure, outlined in the Machine De-
hydration section, page 48.
h. Slowly raise the system pressure to a maximum of 210
psig (1448 kPa) but no less than 68 psig (469 kPa)
[35 psig (241 kPa)] by adding refrigerant. Proceed with
the test for small leaks (Steps3-7).
3. Check the machine carefully with an electronic leak de-
tector, halide torch, or soap solution.
4. Leak Determination — If an electronic leak detector in-
dicates a leak, use a soap bubble solution, if possible, to
confirm. Total all leak rates for the entire machine. Leak-
age at rates greater than 1 lb/year (0.45 kg/year) for the
entire machine must be repaired. Note total machine leak
rate on the start-up report.
5. If no leak is found during initial start-up procedures, com-
plete the transfer of refrigerant gas from the storage tank
to the machine. Retest for leaks.
6. If no leak is found after a retest:
a. Transfer the refrigerant to the storage tank and per-
form a standing vacuum test as outlined in the Stand-
ing Vacuum Test section, page 48.
b. If the machine fails this test, check for large leaks
(Step 2b).
c. Dehydrate the machine if it passes the standing vacuum
test. Follow the procedure in the Machine Dehydra-
tion section. Charge machine with refrigerant.
7. If a leak is found, pump the refrigerant back into the stor-
age tank, or if isolation valves are present, pump into the
vessel that is not leaking.
Transfer the refrigerant until machine pressure is at least
equal to the pressure specified by the EPA under 40CFR
Part 82.
Repair the leak and repeat the procedure, beginning from
Step 2h to ensure a leaktight repair. If machine is opened
to the atmosphere for an extended period, evacuate it be-
fore repeating leak test.
40
Comentários a estes Manuais